Skip to main content
Industrial inspection ROV with twin LED headlights hovering in turbid teal-green reservoir water, illuminating a corrosion-induced spalled zone with exposed corroded rebar stubs on the upstream face of an aging concrete gravity dam
Technical Brief 14 min read ·

Underwater Concrete Repair for Aging Dams: Methods, Materials, and Decision Framework

India's Dam Rehabilitation and Improvement Project (DRIP) completed physical rehabilitation of 223 dams under Phase I (2012-2021) at a cost of Rs 2,567 crore. The combined Phase II and Phase III, operational since October 2021 with a Rs 10,211 crore outlay co-financed by the World Bank and the Asian Infrastructure Investment Bank, target 736 dams across 19 states and two central agencies. A significant proportion of these structures have concrete or masonry components that have deteriorated below the waterline, in zones that cannot be dewatered without taking the reservoir out of service. Underwater concrete repair is among the most technically demanding operations in dam rehabilitation. The repair material must resist washout during placement, bond to deteriorated substrate in saturated conditions, and achieve long-term durability in a permanently submerged environment. Getting it wrong means the repair fails silently, underwater, where it cannot be easily inspected. This technical brief examines the five principal methods for underwater concrete repair on dams, the materials and standards governing each, and a decision framework for selecting the right technique based on the repair's location, volume, structural significance, and access constraints.

AS

A.K. Sthapak

Managing Director, PCCI

underwater repair dam rehabilitation concrete repair tremie concrete

Most concrete deterioration on dams happens where you can see it: the downstream face, the spillway chute, the stilling basin floor during dewatered inspections. But some of the most consequential damage occurs below the waterline, on surfaces that remain permanently submerged and can only be assessed through ROV inspection or diver survey. Repairing these zones is fundamentally different from conventional above-water concrete repair. The substrate is saturated. The formwork must resist hydrostatic pressure. The repair material must resist washout during placement. And quality verification is limited to what cameras, cores, and acoustic methods can tell you after the fact.

ACI PRC-546.2-20 (also catalogued as ACI 546.2R-20), titled Guide to Underwater Repair of Concrete, is the primary reference document, providing comprehensive guidance on materials, methods, formwork, and inspection for submerged concrete repair. For Indian dam projects, IS 456 and IS 457 provide the structural framework, but project-specific underwater repair specifications typically reference ACI 546.2R because the Bureau of Indian Standards has not published a dedicated equivalent standard. The United States Bureau of Reclamation (USBR) also maintains decades of technical references on underwater repair of hydraulic structures, particularly spillway tunnels and stilling basins.

With DRIP Phase II and Phase III covering 736 aging dams across 19 Indian states and two central agencies, and with most of these structures being composite dams more than 25 years old, the demand for competent underwater concrete repair is growing faster than the available expertise to deliver it.

Key Facts at a Glance

  • Primary standard: ACI PRC-546.2-20 / ACI 546.2R-20, Guide to Underwater Repair of Concrete. Indian framework: IS 456 and IS 457 for structural design; no BIS standard dedicated to underwater concrete repair.
  • Five principal methods: tremie concrete, preplaced aggregate concrete (PAC), anti-washout concrete, epoxy injection, and pumped concrete.
  • Strength achieved underwater: typically 70 to 90 percent of equivalent dry-placed concrete compressive strength, depending on method and execution quality.
  • DRIP Phase I (2012-2021): 223 dams rehabilitated across seven states (Jharkhand, Karnataka, Kerala, Madhya Pradesh, Odisha, Tamil Nadu, Uttarakhand) at Rs 2,567 crore, financed by the World Bank.
  • DRIP Phase II and III (2021-2031): 736 dams across 19 states and two central agencies (Bhakra Beas Management Board and Damodar Valley Corporation), Rs 10,211 crore combined outlay, co-financed by the World Bank and the Asian Infrastructure Investment Bank.
  • Earliest large-scale dam application of PAC: Hoover Dam Arizona spillway tunnel, repair started shortly after the October 1941 erosion event; original cavity approximately 35 m long by 9 m wide and up to 14 m deep (USBR).

Five Principal Methods

1. Tremie Concrete

Tremie concrete is placed underwater through a pipe (the tremie) that maintains a seal below the concrete surface throughout placement. The pipe is initially charged with concrete, lowered to the repair area, and then slowly raised as fresh concrete flows from the bottom up, displacing water without mixing with it.

The method is best suited for large-volume repairs where the tremie can be positioned without frequent relocation. Tarbela Dam in Pakistan remains the most-cited historical example: after the 1974 cavitation event destroyed the 2-metre-thick reinforced concrete lining of one of its irrigation tunnels, the remediation campaign deployed large volumes of tremie-placed and steel-fibre-reinforced concrete in the tunnels, stilling basins, and spillway plunge pools, in one of the largest underwater concrete repair operations in dam engineering history.

Advantages:

  • High placement rates for large volumes
  • Uses conventional concrete batching equipment
  • Well-established methodology with extensive precedent

Limitations:

  • Requires maintaining tremie seal continuously; loss of seal causes washout and contamination
  • Not practical for thin or geometrically complex repairs
  • Substrate preparation is limited to what divers or ROVs can achieve

Mix design considerations: Tremie concrete requires high workability (typically 150 to 200 mm slump) with cohesion sufficient to resist washout. This is achieved through higher cementitious content than conventional concrete, fine aggregate enrichment, and sometimes anti-washout admixtures. The mix must flow freely through the tremie pipe without segregation while maintaining sufficient paste volume to displace water at the placement front.

2. Preplaced Aggregate Concrete (PAC)

Preplaced aggregate concrete separates the placement process into two stages. First, clean, graded coarse aggregate is placed into formwork, either dry (if the area can be temporarily dewatered) or submerged. The aggregate packs densely under its own weight, forming a structural skeleton. Second, a highly fluid cement-sand grout is pumped from the bottom up through embedded grout pipes, filling all void spaces and displacing water as it rises. Pumping continues until grout appears at all vent pipes, confirming complete void filling.

The technique has a distinguished history in dam repair. The Hoover Dam Arizona spillway tunnel was repaired starting in 1941, immediately after a maximum flow of 38,000 cubic feet per second eroded a cavity approximately 35 metres long, 9 metres wide, and up to 14 metres deep (115 ft × 30 ft × 45 ft, totalling about 818 m³ of removed material) using the Prepack and Intrusion process, a preplaced-aggregate technique developed at the time (USBR). Barker Dam in Colorado (built 1909-1910, approximately 53 m / 175 ft high) was repaired in 1946 using preplaced aggregate concrete, with grout intrusion completed after about ten days.

Advantages:

  • Minimal segregation because the aggregate is stationary during grouting
  • Excellent bond to existing concrete and to reinforcement
  • High density and low porosity in the finished product
  • Effective in submerged conditions; grout displaces water upward through the aggregate voids

Limitations:

  • Requires formwork and grout pipe installation, which is labour-intensive underwater
  • Aggregate gradation is critical: too fine blocks grout flow; too coarse leaves unfilled voids
  • Not suited for thin repairs (minimum practical thickness approximately 150 mm)

Best applications on dams: Stilling basin floor repair, pier and abutment restoration, filling large erosion cavities, and upstream face resurfacing. The technique excels when the repair volume exceeds approximately 1 m3 and the geometry permits formwork installation.

3. Anti-Washout Concrete

Anti-washout admixtures (AWAs) modify the rheology of fresh concrete to resist segregation and washout when placed underwater without a tremie seal. The concrete can be placed by pump, skip, or even free-fall through water while retaining its cementitious paste. AWAs are typically cellulose-based or welan gum-based polymers that increase the viscosity and cohesion of the mix. ASTM C1621 provides the standard test method for evaluating the passing ability of self-consolidating concrete, which is relevant to assessing AWA-modified mix performance.

Research has shown that incorporating ground granulated blast-furnace slag (GGBS) enhances anti-washout properties through latent hydraulic reactions, with underwater concrete typically using slag with Blaine fineness in the 4,000 to 6,000 cm²/g range (450 to 600 m²/kg).

Advantages:

  • Eliminates the need to maintain a tremie seal, simplifying placement logistics
  • Effective for medium-volume repairs in locations where tremie positioning is difficult
  • Compatible with pumping, reducing the need for direct diver involvement during placement

Limitations:

  • AWA-modified concrete typically achieves 70 to 85% of the strength of equivalent dry-placed concrete
  • Higher admixture cost increases material price per cubic metre
  • Requires careful mix proportioning; excessive AWA dosage can reduce strength and increase setting time

4. Epoxy Injection and Epoxy Grout

Epoxy systems are the standard for structural crack repair underwater. The epoxy resin is formulated to cure in the presence of water and is injected into cracks under pressure, bonding the crack faces and restoring structural continuity. When mixed with graded silica sand, epoxy forms a mortar suitable for patching and filling voids.

Advantages:

  • Bond strength can exceed the tensile strength of the parent concrete
  • Waterproof once cured, sealing the crack against further water ingress
  • Applicable to cracks as narrow as 0.05 mm (per ACI 224.1R guidance) that are too fine for cementitious repair

Limitations:

  • Expensive relative to cementitious materials; not practical for large-volume repairs
  • Requires clean, stable crack surfaces; poorly prepared substrates yield poor bond
  • Limited pot life and sensitivity to water temperature; cold dam environments slow cure

Best applications on dams: Structural crack repair in dam faces, gallery walls, and gate piers where water tightness and structural bond are essential. Also used for anchoring bolts and reinforcing steel into existing concrete underwater.

5. Pumped Concrete

Pumped concrete is batched above water and delivered underwater through a pipeline, relying on pump pressure and sometimes gravity flow to reach the repair location. It is simpler than tremie placement but offers less control over the placement front.

Advantages:

  • Fast placement rates for accessible locations
  • Uses standard pump equipment available on most dam sites

Limitations:

  • Higher risk of washout compared to tremie or PAC
  • Requires anti-washout admixtures for effective performance in open-water conditions
  • Limited to applications where the pump line can reach the repair area without excessive pressure loss

Decision Framework: Selecting the Right Method

The choice of underwater repair method depends on four primary factors:

FactorTremiePACAnti-WashoutEpoxyPumped
Repair volume > 5 m3✅ Best✅ Good⚠️ Possible❌ Not suited✅ Good
Repair volume < 1 m3❌ Impractical❌ Impractical✅ Good✅ Best⚠️ Possible
Structural crack repair✅ Best
Deep erosion cavity✅ Good✅ Best⚠️ Possible⚠️ Possible
Complex geometry❌ Difficult⚠️ Possible✅ Good✅ Good⚠️ Possible
Minimal diver access✅ Good❌ Needs divers✅ Good⚠️ Needs divers✅ Good
Structural strength critical✅ Good✅ Best⚠️ Moderate✅ Best (bond)⚠️ Moderate

For most stilling basin repairs, where large volumes of eroded concrete must be replaced in a submerged environment, PAC or tremie concrete are the preferred methods. For crack treatment in dam faces and gate structures, epoxy injection is the standard. For medium-volume repairs in geometrically complex locations (gate slots, transition zones), anti-washout concrete offers the best flexibility.

Quality Assurance for Underwater Repairs

Quality control for underwater concrete repair is inherently more challenging than for above-water work. The engineer cannot observe the placement directly, cannot vibrate the concrete conventionally, and cannot readily assess bond quality after placement.

Pre-Repair Requirements

  1. Condition survey: ROV or diver inspection to map the full extent of deterioration, including crack patterns, erosion depth, joint separation, and any exposed reinforcement.
  2. Substrate preparation: Removal of loose, deteriorated, or contaminated concrete to sound substrate. Underwater, this typically uses hydro-demolition (high-pressure water jetting) rather than mechanical chipping, because the water environment facilitates debris removal.
  3. Trial placement: For large repairs, a trial placement at a representative depth and orientation confirms that the selected method and mix achieve acceptable results before committing to the full repair.

During Placement

  • Maintain continuous monitoring of tremie seal (for tremie concrete) or grout pressure and flow rate (for PAC)
  • Monitor concrete temperature if large volumes are placed in confined formwork
  • Record placement rate, material quantities, and any interruptions

Post-Repair Verification

  • ROV survey of completed repair surface to verify coverage and surface quality
  • Core extraction from accessible portions of the repair to verify compressive strength, density, and bond
  • Acoustic testing (ultrasonic pulse velocity) across the repair-substrate interface to check for voids or debonding
  • Seepage monitoring if the repair is intended to reduce water ingress through the dam body

Implications for Indian Dam Owners

The Dam Safety Act 2021, supported by the Central Water Commission’s institutional framework, places clear obligations on dam owners to maintain their structures in safe operating condition. For the 736 dams targeted under DRIP Phase II and Phase III across 19 states and two central agencies, many have concrete components that have deteriorated below the full supply level and require underwater intervention. Durability and service-life considerations sit at the centre of every repair specification.

The challenges are practical. Most state dam safety organisations have limited experience specifying and supervising underwater concrete repair. The contractor base in India with proven underwater concrete repair capability on dams is small. And the materials (AWA admixtures, underwater-curable epoxies, specialty grouts) are available but require correct specification and application.

This is where consulting expertise matters. Specifying the right repair method, selecting appropriate materials, designing the QA/QC programme, and supervising execution underwater requires a combination of materials science knowledge, hydraulic engineering understanding, and field experience that goes beyond standard civil construction practice.

PCCI’s troubleshooting and rehabilitation practice draws on leadership experience across South Asia’s most demanding hydroelectric projects, where concrete performance in severe hydraulic environments is not optional. For dam owners facing underwater repair decisions under DRIP or any other rehabilitation programme, the starting point is always the same: understand exactly what has deteriorated, why it has deteriorated, and then select the repair approach that addresses the root cause rather than just the symptoms.


For expert guidance on underwater concrete repair specification and supervision for your dam rehabilitation project, contact PCCI’s consulting team.

Share this insight:

Frequently Asked Questions

Key Questions Answered

What is the primary standard governing underwater concrete repair?
ACI PRC-546.2-20, also catalogued as ACI 546.2R-20, titled Guide to Underwater Repair of Concrete, is the primary reference document. Published by ACI Committee 546 (Concrete Repair), it provides comprehensive guidance on the selection and application of materials and methods for repairing and strengthening concrete structures underwater. The guide covers formwork design for submerged conditions, material selection criteria (including anti-washout admixtures, epoxy systems, and cementitious grouts), placement methods (tremie, pumped, preplaced aggregate), inspection and quality control procedures, and case studies of dam-specific applications. For Indian dam projects, IS 456 and IS 457 provide the structural design framework, but project-specific specifications for underwater repair typically reference ACI 546.2R for methodology because the Bureau of Indian Standards has not published an equivalent dedicated standard for underwater concrete repair. The United States Bureau of Reclamation (USBR) technical references also provide detailed guidance on underwater repair of hydraulic structures, particularly for spillway and stilling basin applications.
Can underwater concrete repair achieve the same strength as dry-placed concrete?
Not typically at the same age, but adequately for most rehabilitation purposes. Underwater-placed concrete generally achieves 70 to 90% of the compressive strength of equivalent dry-placed concrete, depending on the method and materials used. Tremie concrete with proper mix design and placement technique can approach 90% of equivalent dry-placed strength. Preplaced aggregate concrete achieves comparable ultimate strength because the grout fills a pre-existing aggregate skeleton under controlled conditions, minimising segregation. Anti-washout concrete using AWA admixtures retains more cementitious paste than conventional concrete placed underwater, improving both strength and durability. Epoxy-based systems can achieve bond strengths exceeding the tensile strength of the parent concrete, making them suitable for structural crack repair. The critical factor is not the method but the quality of execution: proper substrate preparation, controlled placement rates, maintaining tremie seal or grout pressure, and avoiding washout of cementitious material. A well-executed underwater repair using modern materials and methods can provide a durable, structurally adequate repair. A poorly executed repair, regardless of method, will fail.
How is an underwater repair area on a dam inspected before and after repair?
Pre-repair inspection uses remotely operated vehicles (ROVs) equipped with high-definition cameras and sonar to survey the deteriorated area. The ROV produces video footage and still images of the concrete surface, documenting crack patterns, spalling extent, erosion depth, joint separation, and any exposed reinforcement. Divers may supplement ROV data with tactile assessment (sounding for delamination) and sample collection in accessible areas. For depth measurement of erosion cavities, sonar profiling or diver-operated measurement tools are used. Post-repair inspection follows the same protocol: ROV survey of the completed repair surface to verify coverage, surface finish quality, and absence of visible defects. For critical structural repairs, core samples may be extracted from the repaired zone after curing to verify compressive strength, bond strength, and density. Acoustic methods (pulse velocity) can assess the integrity of the repair-to-substrate interface. The post-repair inspection creates a digital baseline for monitoring repair performance over time, using the same AI-assisted drone and ROV inspection technologies described in the companion article on computer vision for dam inspection.
What causes concrete deterioration below the waterline on dams?
Several mechanisms cause underwater concrete deterioration on dams. Abrasion and erosion occur in spillway chutes, stilling basins, and outlet works where high-velocity water carries sediment and debris against the concrete surface. Cavitation causes damage at locations where water pressure drops below vapour pressure, typically at surface irregularities, gate slots, and transitions in hydraulic profile; the collapsing vapour bubbles generate intense local pressures that pit and crater the concrete surface. Freeze-thaw cycling affects concrete at the waterline zone (the splash zone) where water-saturated concrete is repeatedly frozen and thawed. Alkali-aggregate reaction (AAR) can occur in any zone but progresses more aggressively in the presence of moisture, making submerged concrete particularly vulnerable. Chemical attack from aggressive water (low pH, high sulphate, or high CO2 content) dissolves cement paste and weakens the concrete matrix over time. Leaching occurs when water flowing through cracks or porous concrete dissolves calcium hydroxide, reducing the concrete's pH and eventually its structural integrity. On Indian dams, particularly those more than 25 years old, multiple mechanisms often act simultaneously, making condition assessment the critical first step before any repair is designed.
How does DRIP Phase II affect the demand for underwater concrete repair in India?
DRIP Phase II significantly increases demand. Under Phase I (April 2012 to March 2021), physical rehabilitation of 223 dams was completed across seven states (Jharkhand, Karnataka, Kerala, Madhya Pradesh, Odisha, Tamil Nadu, and Uttarakhand) at a cost of Rs 2,567 crore. The combined Phase II and Phase III, operational since October 2021, target 736 dams across 19 states and two central agencies (Bhakra Beas Management Board and Damodar Valley Corporation), with a Rs 10,211 crore outlay (Phase II Rs 5,107 crore co-financed by the World Bank and the Asian Infrastructure Investment Bank at US$ 250 million each; Phase III Rs 5,104 crore from the World Bank at US$ 500 million). Implementation runs through 2031. As of 31 March 2025, major physical rehabilitation works had been completed at 43 dams under Phase II. A significant proportion of these structures are composite dams (masonry or concrete gravity sections combined with earthen embankments) more than 25 years old, with concrete or masonry deterioration below the full supply level in zones that cannot be dewatered without reservoir drawdown or temporary cofferdams. Project interventions include seepage reduction through upstream pointing, grouting, and geomembrane installation, plus crack treatment in the dam body and drainage system upgrades. Project-specific research has included DRIP-supported laboratory studies (for example, on Mahan Dam) evaluating UV-resistant epoxy repair materials, joint sealants for monolith-joint seepage control, and high-abrasion-resistant coatings for spillway glacis repair. The scale of the programme is creating demand for consulting firms with expertise in underwater repair specification, material selection, and quality assurance, since many state dam safety organisations implementing DRIP have limited prior experience with underwater concrete repair techniques.
AS

About the Author

A.K. Sthapak

Managing Director, PCCI

With 40+ years of hands-on experience in concrete technology for hydroelectric infrastructure, Mr. A.K. Sthapak has delivered technical consulting on projects totalling 4,000+ MW across South Asia. He is a lifetime achievement awardee of the Indian Concrete Institute.

Newsletter

Concrete Pulse

Stay ahead on concrete technology. Subscribe to our weekly newsletter. Field-tested insights on mass concrete, dam engineering, and QA/QC, delivered straight to your inbox.

Past Issues

Free. No spam. Unsubscribe anytime.

Talk to a concrete specialist within 24 hours.

Whether you're at pre-tender feasibility or mid-construction troubleshooting. Whether your project is in India, Bhutan, Nepal, or beyond.